Project Overview

Coastal Electrical Services & Renewable Energy were appointed by N R Burton Builders to deliver a complete electrical and low-carbon energy solution for a new build private residence. The project combined modern electrical design, smart energy systems, and high-level safety and compliance.

Project Highlights

First Fix Electrical Works

The first fix stage focused on infrastructure, containment, and future-proofing the property.

Works included:

  • Full cable installation for:
  • Power circuits
  • Lighting circuits
  • Smoke, heat & carbon monoxide detection
  • Data & TV points
  • CCTV & intruder alarm systems
  • Installation of back boxes and accessory positions
  • Consumer unit positioning and main earthing/bonding provisions
  • Wiring for:
  • EV charging point
  • Solar PV system
  • Battery storage system
  • External supplies prepared for garden and feature lighting
  • Containment routes designed to allow for future upgrades

All cabling was installed in accordance with BS 7671 wiring regulations and coordinated closely with other trades to ensure a clean, safe installation.

Second Fix Electrical Works

At second fix, the installation was completed with all accessories, fittings and equipment.

Works included:

  • Installation of:
  • Sockets & switches
  • Internal and external lighting fittings
  • Consumer unit & protective devices
  • Final connection of:
  • Smoke, heat & carbon monoxide alarms
  • Data outlets and media points
  • EV charger final connection and configuration
  • Integration of renewable energy systems with household distribution

A high standard of finish was maintained throughout, ensuring both performance and aesthetics matched the quality of the build.

CCTV System

A modern CCTV system was installed to provide full perimeter and property coverage.

  • External high-definition cameras
  • Discreet cabling routes
  • Remote viewing capability via mobile device
  • DVR/NVR located in a secure internal position

The system provides enhanced security and peace of mind for the homeowner.

Intruder Alarm System

A fully compliant intruder alarm system was installed including:

  • Control panel
  • PIR motion detectors
  • Door contacts
  • Internal sounder
  • External siren

The system was designed for reliability, ease of use and future expandability.

EV Charger Installation

To support low-carbon transport:

  • Dedicated EV charging circuit installed
  • Charger positioned for convenient vehicle access
  • Load considerations integrated with main supply and solar system

This allows efficient home vehicle charging while maintaining electrical safety and capacity.

Solar PV & Battery Storage

The property was equipped with a renewable energy system to reduce grid reliance.

  • Roof-mounted Solar PV array
  • Hybrid inverter installation
  • Battery storage system for energy retention
  • System integrated with the property’s distribution board

This setup enables:

  • Self-consumption of solar generation
  • Battery charging from excess solar
  • Reduced energy bills
  • Lower carbon footprint

Installation completed in line with MCS standards.

Internal & External Lighting

A complete lighting design was delivered:

Internal

  • General lighting
  • Feature lighting
  • Energy-efficient LED fittings

External

  • Security lighting
  • Garden and pathway lighting
  • Architectural feature lighting

Lighting circuits were designed for both practicality and visual impact.

Testing & Commissioning

Upon completion, full inspection, testing and commissioning were carried out including:

  • Dead testing
  • Live testing
  • RCD/RCBO verification
  • Functional testing of all systems
  • Solar PV and battery system commissioning

All results recorded and certified.

Certification & Compliance

The project was completed to the highest standards and fully certified:

  • NICEIC approved contractor
  • Electrical Installation Certificate (EIC)
  • Part P Building Regulations compliance
  • MCS Certification for Solar PV installation

Outcome

This installation delivered a safe, efficient, and future-ready electrical system, combining modern living convenience with renewable energy technology. The collaboration with N R Burton Builders ensured a seamless build process and a high-quality finish throughout.

From site

Photographs and footage from the job.

A vaulted kitchen and dining room with three rooflights, LED downlights, island pendants and glazed doors to the garden
A vaulted kitchen with two rooflights, LED downlights, three glass pendants over the island and under cabinet lighting
A living room with recessed LED downlights, a wood burner in the chimney breast and glazed doors to the garden
A tiled room with recessed LED downlights, double sockets below the windows and a heating controller by the door
A utility room with recessed LED downlights, a ceiling extractor, a washing machine and sink, the back door beyond
Rear of the new brick and dark clad home, with bifold doors opening onto a new porcelain patio
Two CES vans on the gravel drive of the new brick home, beside its dark clad wing and double garage
Looking up at a bathroom ceiling with an extractor fan, a ceiling sensor, recessed downlights and a glass shower below
A large vaulted bedroom with a chandelier, fitted wardrobes, double sockets and a light switch, the landing beyond
All black solar panels on tilt frames across the flat roof beside the brick gable, a CES van parked beyond
All black solar panels on low tilt frames across a grey flat roof beside the new home's brick wall
Two workers on stepladders at ceiling height in a double garage, LED batten lights lit and tools below
A SolaX hybrid inverter over a stacked battery, with isolators and a SolaX EV charger beside, on a garage wall
Rows of all black solar panels on tilt frames covering a flat roof, looking out over neighbouring houses and trees
An upstairs landing with a sloping ceiling, recessed downlights and a ceiling alarm still in its blue dust cover